Question: In SAP how does a user execute the MRP run for a material?
Answer: The entire purpose of MRP is to plan for a material. The MRP can be executed using the transaction code MD02. MRP Material Requisition Planning can be done for a single material item or a multilevel plan can be run for a material within a plant. But, what exactly does MRP do. Material Requisition Planning creates PR purchase requisitions, PO purchase orders, or planned orders for the material. This is done on the basis of the settings selected in the transactions. To take an example, a particular material item may be procured externally, in such a case, an MRP run creates requirements for that material through the respective plant from a sales document.
Sunday, January 07, 2007
MRP Materials Requisition Planning MD02..
Posted by Sundowns at 8:48 PM
Subscribe to:
Post Comments (Atom)
1 comment:
single item, single level ....static and dynamic lists